New Hampshire state flagNHEPA-Administered

SWPPP Requirements in New Hampshire

New Hampshire lacks NPDES authorization; EPA Region 1 administers the Construction General Permit directly. For sites disturbing 100,000+ sq ft (approximately 2.3 acres), a separate NH Alteration of Terrain (AoT) permit from NH DES is required and includes its own erosion control plan review. The Shoreland Water Quality Protection Act imposes additional restrictions within 250 feet of public waters.

Data Note: This page contains general guidance for New Hampshire. We are actively verifying state-specific details. Last reviewed: 2026-04-10. Contact a local consultant for current requirements.

New Hampshire SWPPP Key Facts

  • EPA CGP administered by EPA Region 1 — no state NPDES permit
  • $0 NOI fee under EPA CGP
  • NH Alteration of Terrain (AoT) permit required for 100,000+ sq ft
  • AoT permit fees range from $600 to $10,000+ based on project size
  • Shoreland Water Quality Protection Act applies within 250 feet of public waters

Administering Agency

Agency
U.S. Environmental Protection Agency Region 1 (EPA Region 1)
Phone
617-918-1111
Email
r1-npdes@epa.gov

Permit Details

Permit Name
EPA 2022 Construction General Permit (CGP)
Permit Number
CTR100000
Effective Date
2022-02-17
Expiration Date
2027-02-16
Permit Document
View Current Permit

SWPPP Thresholds & Triggers

Acreage Threshold
1 acre or more under EPA CGP; NH Alteration of Terrain (AoT) permit required for 100,000 sq ft (2.3 acres) or more of disturbed area

NH Alteration of Terrain (AoT) permit from NH DES required for disturbances of 100,000+ sq ft. Shoreland Water Quality Protection Act applies within 250 feet of public waters.

Inspection Requirements

Inspection Frequency
At least every 7 days and within 24 hours of a 0.5-inch or greater storm event (per EPA CGP)
Rain Event Threshold
0.5 inches within 24 hours
Certified Inspector
Not required by state

NH DES administers the Alteration of Terrain permit separately from NPDES. The AoT permit has its own erosion control plan requirements. Both permits may run concurrently for larger sites.

Penalties & Enforcement

Max Civil Penalty (Per Day)
$25,000 per day per violation (federal CGP); NH RSA 482-A penalties up to $10,000/day
Criminal Penalties
Up to $50,000/day and imprisonment under CWA for federal violations

EPA Region 1 enforces CGP; NH DES enforces AoT permit and Shoreland Act violations independently.

Permit Fees

NOI Filing Fee
$0 (EPA CGP)
NOT Filing Fee
$0
Other Fees
NH Alteration of Terrain permit fee: $600–$10,000+ depending on acreage

How New Hampshire Differs from Federal Requirements

  • NH has no NPDES authorization — EPA CGP applies directly
  • NH Alteration of Terrain permit adds a state layer not present in federal CGP
  • Shoreland Water Quality Protection Act is NH-specific
  • No state fee for NPDES coverage; AoT fee is separate

SWPPP Tips for New Hampshire

  • Apply for AoT permit simultaneously with EPA CGP NOI — NH DES review can take 4–8 weeks
  • Include Shoreland Act compliance documentation in erosion control plans for lakeside or riverfront projects
  • NH DES requires separate E&SC Plan under AoT with specific design standards

New Hampshire SWPPP FAQs

Is the NH Alteration of Terrain permit the same as NPDES coverage?+

No. They are separate permits. EPA CGP covers NPDES stormwater discharge requirements; AoT permit covers NH-specific land disturbance and erosion control requirements. Both may be required for larger sites.

What triggers the Shoreland Water Quality Protection Act?+

Any earth disturbance, construction, or vegetation removal within 250 feet of a public water body (lakes, ponds, rivers) triggers the Shoreland Act, requiring a permit from NH DES.

Find a SWPPP Consultant in New Hampshire

Tell us about your project and we'll connect you with a qualified environmental consultant — free, no obligation.

We'll only call if you ask us to.

Free, no-obligation match. Your info is kept confidential.